Good morning!
- The work continues on trying to identify the memory leak. We reduced the problem by resolving multiple situations where references were being held unnecessarily, but there's still more research to do. Since the leak is still occurring but it's not as bad, that suggests that I reduced the size of the leaking objects, but still did not find the cause of the leak. After this is resolved, which might take many days, then I can look into the issues where some miners are reporting disconnections from "live status" displays.
- I determined the cause of the electricity calculations being incorrect, and the resolution is complex, requiring us to track which worker submitted which share. The upside is that once finished, the workers will be able to be sorted by invalid share count, as some miners have requested.
- Chris is continuing to catch up from his backlog. He said goodbye to Novaexchange yesterday, finishing paying out customers in all 160 coins that are no longer offered anywhere, deleting the coins from our server, and liquidating whatever was leftover. His remaining tasks before getting up to date will be linking our Atlassian tools together, then resolving our DKIM E-Mail issue, then resolving the support tickets from October and November that remain in the old system, and then resolving the newer tickets. After he has caught up, he'll then be able to finally add new exchanges to improve profits.
- We're trying to determine whether we should next hire people to fix minor issues, or save to start building the million dollar reserve we will need to offer SHA-256 mining. The million dollars comes from the idea that we need to have three blocks of reserve available to be 99% sure we won't have to shut down due to bankruptcy, and assumes a bitcoin value of $20,000 with the minimum fee for a simple transaction rising from $8 now to $150 in March. Comments?